As Built Drawings and Operation and Maintenance Manuals
- 20 days before we apply for works completion, you will submit a draft copy of executed drawings and operation and maintenance manuals to us for approval.
- If there are any, we will ask for changes within 10 days from your submission.
- You must make the required changes and resubmit within 5 days.
- The submission may be required to be uploaded and/or generated through the project’s specified Document Management System
- If you don’t do the above, in the time specified, we will get it done for you and then charge you for it.